Summer 2017 Construction Update

Mammoth Community Water District Construction Crews have had a productive summer, completing a variety of both scheduled and non-scheduled projects. The crew’s final day of the construction season was October 27th. The crew replaced twenty-one service laterals along Main St. and Sierra Manors Rd., installed isolation valves on Lake Mary Rd., replaced a fill control valve and vault near Snowcreek Golf Course, and replaced 2000’ of distribution pipeline in the Timber Ridge Condo area. We thank you for your patience while work was completed, and look forward to the 2018 construction season. For more information, please contact Matt Jaroslawski at 760-934-2596 ext. 251.

 